11/03/2026: Project Update
The Village is aware that conceptual plans from one of the four finalist development teams for 111 E. Busse Avenue have recently been shared on social media. The Village clarifies that no developer has been selected and no redevelopment proposal has been approved.

The Village Board is scheduled to complete interviews with the finalist teams on Tuesday, November 10, 2026, in closed session. These interviews are not open to the public to allow the Village Board to privately discuss setting the financial terms of selling publicly owned property to a developer, and to protect the proprietary designs and financial information of the competing development firms. 

Following the interviews, the Village Board will determine the next steps, which could include selecting a preferred developer, requesting additional information, or choosing not to move forward with any proposal.

If the redevelopment process advances, we anticipate opportunities for public input, including an open house with the selected developer and the formal public hearing and approval process involving the Planning and Zoning Commission and Village Board.

09/03/2026: Property Tour
Village staff met with parties interested in the development of the 111 E. Busse Property and provided a guided walking tour to see the space. 

08/20/2026: Publication of RFQ
The Village was seeking statements of qualifications from experienced development teams interested in partnering with the Village on redevelopment. Highly qualified development partner with demonstrated experience in for sale residential development; adaptive reuse of existing buildings for residential purposes; mixed use development; and the development and leasing of high-quality retail/restaurant/entertainment uses on an expedited basis were encouraged to apply. Elected officials and staff envision the property as a transformative mixed use redevelopment and signature addition to Downtown Mount Prospect. The selected development partner will work collaboratively with the Village to evaluate redevelopment alternatives and refine a development program that advances the Village’s land use, economic development, design, housing, and fiscal objectives. Submittal Deadline:  September 18, 2026

Request For Proposal (RFP) Process
07/11/2025: RFP Extension
Due to significant interest and multiple requests for additional time, staff elected to extend the deadline for submitting proposals for the 111 E Busse RFP. The submission deadline was extended by two weeks, with the proposal due date shifted to Friday, July 25th.

06/19/2025: RFP Walk Through Question Responses
Staff met with multiple developers and interested citizens on June 19 to have an onsite exterior tour of the 111 Busse property. This meeting presented an opportunity for staff to be asked questions about the RFP that is currently set to close on July 11. A follow up answering all questions from interested parties on the walkthrough was given by staff shortly after the walkthrough. 

05/21/2025: RFP Published
With the property officially under Village ownership, the Village is issuing a Request for Proposals (RFP) from qualified developers to reimagine and reconstruct this key site. Located in a prime location, the 111 E. Busse site offers unparalleled potential to create a signature destination development that aligns with Mount Prospect’s vision for a vibrant, walkable, and economically robust downtown.  


03/11/2025: Discussion regarding visions for redeveloping the property at the South East Corner of Busse Avenue and Emerson Street (111 E. Busse Ave).
Staff is seeking input from the Village Board on key elements to consider for the redevelopment of the recently acquired 2.15-acre property located at the southeast corner of Busse Avenue and Emerson Street, also known as "111 Busse Ave" or the "Busse and Emerson Site."

Village Acquires 111 E. Busse Avenue
The property is located in the heart of Downtown Mount Prospect and is the site of a vacant six-story office building, formerly housing a Chase Bank. The property is 94,896 SF or 2.18 acres in a prime location in downtown Mount Prospect. The building has been vacant for several years and the underlying owner(s), lender and title company were in litigation in the Circuit Court of Cook County. After negotiations, all parties agreed to a Purchase and Sale Agreement that will authorize the Village to acquire the property for $5.0 million. The transaction closed on Wednesday, May 14, for the 2.15-acre site prominently situated in the heart of downtown.