TENTATIVE SCHEDULE
Phase I April 15 – April 30
Algonquin Road from Busse Road to Dempster Street
Road Closure/Detour
Westbound lanes on Algonquin Road detoured to northbound Busse Road, westbound Golf Road, southbound Arlington Heights Road
Phase II May 1 – May 15
Algonquin Road at Dempster Street intersection
Road closure/detour
Westbound lanes on Algonquin Road detoured to northbound Busse Road, westbound Golf Road,
southbound Arlington Heights Road
Westbound lanes on Dempster Street detoured to northbound Busse Road, westbound Golf Road,
southbound Arlington Heights Road
Eastbound lanes on Dempster Street detoured to eastbound Algonquin Road, northbound Elmhurst
Road
Phase III May 16 – June 30
Algonquin Road from Dempster Street to Cedar Glen Drive
Road Closure
No detour, westbound Algonquin Road lane closure
Phase IV July 1 – July 15
Dempster Street from Busse Road to Algonquin Road
Road Closure/Detour
Westbound lanes on Dempster Street detoured to southbound Busse Road, westbound Algonquin
Road
Phase V July/August 2026
Final cleanup & restoration