The Village of Mount Prospect is operating under emergency protocols dealing with the COVID-19 virus. Village Hall, Public Works, Fire Headquarters and the Community Connections Center are all closed to the public through April 30. For the latest information go to the COVID-19 page or read the latest information in the News section.

VILLAGE PROJECTS

1. STREET RESURFACING PROGRAM
Description: 7 miles of intermittent curb repair and asphalt resurfacing at various locations throughout the Village.  Please visit the Road Resurfacing webpage for details and current updates concerning the program.
Contractor: Arrow Road Construction
Schedule: Start work - April 2020/ Complete Work - November 2020


2. PRIVATE PROPERTY DRAINAGE SOLUTIONS (Various locations throughout the Village)
Description: Install drainage improvements at problem locations.
Cost: $100,000
Contractor: Undetermined / Bid Opening in June
Schedule: Start work - August 2019 / Completion - October 2019

3. SANITARY SEWER MAIN LINING (Various locations throughout the Village)

Description: Rehabilitating 53 Sanitary manholes located in the Fairview Gardens Neighborhood. The Rehabilitation process includes cleaning of the interior manhole, applying grout to open cracks, applying a cementitious coating and finally applying an epoxy coating.

Cost: Contractor $222,350

Inspection : Village Staff

Contractor: Culy Contraction

Schedule: May – June 2020

4.  WATERMAIN IMPROVEMENTS

Description: Replace approximately 6,000 lineal feet of watermain.  Locations include the installation of 8” water main on the 800 and 900 blocks of south Owen ad William Street and the installation of 8” water main on the 600 blocks of south Louis and Albert Street. 

Cost:  Deign $140,000; Construction $2.3 Million
Design Engineer: Burns & McDonnell
Contractor: TBD
Schedule:  Project is currently in design phase.  Anticipate construction starting summer 2020

5.  LEVEE 37 COMPANION STORM SEWER IMPROVEMENTS
Description: 

Cost:
Design Engineer:
Contractor: TBD
Schedule: Project is currently in design phase.  Anticipate construction starting fall 2019

6.  LINCOLN STREET RELIEF STATION REHABILITATION PROJECT

Description: Rehabilitate the 45+ year old Lincoln street relief station. The project includes new and improved submersible pumps and their associated piping, rehabilitating the existing wet well, new operating panel and new underground electrical infrastructure.

Cost: Design & Inspection $59,510 Construction $350,000

Design and inspection engineer: Baxter & Woodman

Contractor: TBD

7. EXTERIOR PAINTING PROJECT (PAINT IT BLACK)

Description: Painting and rehabilitating 46 road poles, 20 pedestrian poles and 2 control cabinets along Northwest Highway and Central Road. The contractor with use a 2-part primer, PPG Amerlock 200 epoxy and a 2-part finish, PPG PSX 700 epoxy gloss on each pole.

Cost: Contractor $40,000

Inspection : Village Staff

Contractor: TBD

Schedule: Summer 2020

 8WELL 4 AND WELL 11 REHABILITATION PROJECT

Description: Rehabilitating two of the Villages five ground water deep wells. The project includes an inspection of the existing conditions of both wells. From the inspection results is what will determine the rehabilitation work that needs to be done

Cost: Contractor $500,000 per deep well

Design and inspection engineer: TBD

Contractor: TBD

Schedule: Summer – Fall 2020

 9FAIRVIEW LIFTSTATION REHAB (100 Block of Horner)

Description: Replacing the existing 50+ year old Fairview Lift Station located in Fairview Gardens. The work includes a new wet well, abandoning of the old wet and dry well, two new submersible pumps and associated piping, a new control cabinet and components and new underground electrical infrastructure.

Cost:$900,000
Design Engineer:  Ciorba
Contractor: TBD
Schedule: Fall 2020

10. MAIN & BUSSE PEDESTRIAN CROSSWALK PROJECT

Description: Improve pedestrian safety at Main and Busse. 
Cost: TBD
Contractor: TBD 
Schedule: Construction to begin in the fall of 2020

11. CDBG SIDEWALK PROGRAM

Description: Remove and replace sidewalk or install new sidewalk at predetermined locations.  
Cost: not to exceed $300,000
Contractor: Schroeder & Schroeder, Inc.
Schedule: Construction to begin spring 2020 through fall of 2020

12. NEW SIDEWALK CONSTRUCTION 

13. ASPEN TRAILS PARK DRAINAGE IMPROVEMENTS

14. EMERSON STREET BRIDGE IMPROVEMENTS

15. PEDESTRIAN SIGNAL IMPROVEMENTS: DOWNTOWN & DEMSTER/LINNEMAN

16. PEDESTRIAN CROSSING IMPROVEMENTS: CENTRAL & EMERSON  

17. PEDESTRIAN CROSSING IMPROVEMENTS: PINE & CENTRAL

18. ALGONQUIN ROAD MIXED USE PATH PHASE 1 STUDY

19. MELAS - MEADOWS BRIDGE PHASE 1 STUDY

20. KLEHM'S ISLAND REHABILITATION

21. NORTHWEST HIGHWAY RESURFACING PROJECT

22. MOTOR CONTROL CENTER REPLACEMENT: BOOSTER STATION 4

23.  MOTOR CONTROL CENTER REPLACEMENT: BOOSTER STATION 5