VILLAGE PROJECTS

1. STREET RESURFACING PROGRAM
Description: 7 miles of intermittent curb repair and asphalt resurfacing at various locations throughout the Village.  Please visit the Road Resurfacing webpage for details and current updates concerning the program.

Contractor: Arrow Road Construction
Schedule: Start work - April 2019/ Complete Work - November 2019


2. PRIVATE PROPERTY DRAINAGE SOLUTIONS (Various locations throughout the Village)
Description: Install drainage improvements at problem locations.
Cost: $100,000
Contractor: Undetermined / Bid Opening in June
Schedule: Start work - August 2019 / Completion - October 2019

3. SANITARY SEWER MAIN LINING (Various locations throughout the Village)
Description: Rehabilitate approximately 28,000 lineal feet of combined and sanitary sewer mains utilizing cured-in-place process.
Cost: $1.2 million
Contractor:  Hoerr Construction
Schedule:  Start work - April 2019 / Completion - June 2019

4.  WATERMAIN IMPROVEMENTS
Description: Replace approximately 8,000 lineal feet of watermain.  Locations include the installation of approximately 4,000 lineal feet of 16 inch water main along Northwest Highway between Maple Street and Fairview Ave.  Additional locations include replacement of 6 inch watermain with 8 inch watermain in portions of the Fairview Gardens subdivision.

Cost:  Deign $250,000; Construction $2.7 - $3.0 million
Design Engineer: Robinson Engineering
Contractor: TBD
Schedule:  Project is currently in design phase.  Anticipate construction starting summer 2019

5.  LEVEE 37 COMPANION STORM SEWER IMPROVEMENTS
Description: 

Cost:
Design Engineer:
Contractor: TBD
Schedule: Project is currently in design phase.  Anticipate construction starting fall 2019

6.  PROSPECT MEADOWS (Forest Avenue) STORM SEWER IMPROVEMENTS
Description:

Cost:  $660,000
Contractor:  TBD
Schedule: Currently out to bid. Anticipate construction starting summer 2019

7.  FAIRVIEW LIFTSTATION REHAB (100 Block of Hoerner)
Description:

Cost:$900,000
Design Engineer:  Ciorba
Contractor: TBD
Schedule: Currently in design phase.  Anticipate construction starting summer 2019

8.  WATER TANK REHABILITATION (112 E Highland Avenue)
Description:

Cost: $600,000
Design Engineer: Burns & McDonnell
Contractor: TBD
Schedule:  Currently in design phase.  Anticipate construction starting fall 2019

9.  RANDVIEW HIGHLANDS STREET LIGHTS PHASE II
Description:

Cost: $180,000
Design Engineer:  HLR
Contractor:  TBD
Schedule:  Currently in design phase.  Anticipate construction starting summer 2019

 10.  PROSPECT MEADOWS STORM SEWER (FOREST AVENUE)
Description: Installation of approximately 2,000 lineal feet of storm sewer pipe ranging in size from 12" to 36" in diameter, regrading of parkway ditches, resurfacing of the Forest Avenue including the construction of traffic calming measures.

Cost: $600,000
Design Engineer:  Mount Prospect Public Works
Contractor:  Mauro Brothers
Schedule:  Construction Starts July 24

 

ILLINOIS DEPARTMENT OF TRANSPORTATION PROJECTS

NORTHWEST HIGHWAY RESURFACING

GOLF ROAD RESURFACING

ALGONQUIN ROAD RESURFACING

 

COOK COUNTY HIGHWAY DEPARTMENT PROJECTS

EUCLID ROAD RESURFACING