 |
|
 |
| Levee 37 |
| |
|
Construction Updates
November 13, 2009
Work continues on
the south portion of the wall just south of Seminole Lane and then farther south
just north of Euclid Avenue. Near Seminole Lane the contractor is working to
complete the pump station and outlet structures prior to the arrival of the
mechanical equipment in the next few months. Photos below on the left show the
pump station and outlet structures from the river side and from above.
And work
activities have intensified on the north section just north of the River Road /
Milwaukee Avenue intersection. Sheet piling is being installed, photos below on
the right, to create a temporary cofferdam that will permit construction of a
closure structure and pump station at that location. The good weather this fall
has been a great benefit to the project allowing the contractor to maintain an
excellent pace for the construction.
 |
 |
 |
 |
|
Click on picture for larger image |
|
|
October 16,
2009
Now is a great
time to see the progress that is being made on the construction of the Levee
and take in the colors of the changing leaves along the Des Plaines River.
As the contractor pushes to finish work along River Road, action will
shortly move to the section along Milwaukee Avenue. Sheet piling is being
pulled and preparation is being made to move it to the Milwaukee Avenue
section to install within the next few weeks. Below are pictures of the
Milwaukee Avenue section where work is soon to begin and a look at the wall
from the roadside near Milwaukee Avenue and a peek at what is behind the
wall.
 |
 |
 |
|
Click on picture for larger image |
|
|
|
October 2, 2009
As
construction of the levee wall continues, backfilling operations are taking
place along the sections of wall that have already been completed. Below are
pictures showing the backfilling operations and near the intersection of River
and Milwaukee where the sod has already been installed and the project has a
finished look.
 |
 |
|
Click on picture for larger image |
|
|
|
September 18, 2009
Construction of
the levee wall is ahead of schedule, with over 3,400 lineal feet of the concrete
wall already completed. Construction of the wall has reached south all the way
to Tano Lane as seen in the picture below on the left. The contractor and is
expected to begin work on the section north of the River Road and Milwaukee
Avenue intersection next month. Also pictured below is a typical section of the
concrete wall form lying down ready to be lifted into place and the reinforcing
bars installed just prior to pouring of the concrete.
 |
 |
 |
|
Click on picture for larger image |
|
|
|
|
|
September 4, 2009
The good weather we have experienced this summer has allowed the project to
proceed without the significant rain interruptions that we would normally
experience. Because of that, approximately 80% of the wall from Milwaukee Avenue
to Euclid Avenue has been constructed. In addition, good progress has been made
on the construction of the pump structures and backflow closure structures just
south of Seminole Lane. Since the levee has been designed to extend from Euclid
Avenue all the way to Palatine Road, work on the section of wall to be built
along Milwaukee Avenue, north of River Road, will need to be coordinated with
IDOT and their Milwaukee Avenue project and will extend into next year. Below
are pictures depicting the wall near Camp McDonald Road and the pump structure
south of Seminole Lane.
 |
 |
|
Click on picture for larger image |
|
|
|
August 21, 2009
Construction of the levee wall continues, including raising of Milwaukee
Avenue just west of the Des Plaines River Bridge. The road itself will be raised
high enough to eliminate the need to close Milwaukee Avenue in the event of a
significant flood. Recently, concrete was poured for the eastbound lanes of the
road. A picture showing the new lanes and the elevated height of the roadway is
shown below.
Work has also started on other less visible, but equally critical elements of
the flood protection project. The obvious flooding problem along the Des Plaines
River is overland flooding when the river swells following significant rain
events with water from the upstream tributary areas, Lake County and
southeastern Wisconsin. However, the northeast section of Mount Prospect has
experienced flooding in the past even when the river has not overtopped River
Road. The storm sewer system from this section of town drains directly into the
river, yet during heavy times when the river has neared flooding stage, it is
these same sewers which have historically provided a conduit for the river’s
flood waters to flow under River Road and into the subdivisions west of the
river. In the early 1990’s, the Village installed backflow devices on the ends
of the subdivisions storm sewers at the Des Plaines River which prevented this
action from occurring. These backflow valves are still in place and working to
protect the subdivisions from river flood waters. Since they are almost 20 years
old, they will be replaced by new valves as part of the levee project. A picture
of the existing valves is shown below.
Another element of the flood protection project is a pumping station to pump
the water that falls within the Village’s subdivisions out into the Des Plaines
River. When the River swells it traps the rainwater in the Village’s storm
sewers that cannot exit out into the river because the backflow valves are
closed. When this happens, you see the Public Works Department bring portable
pumps out to the river and begin pumping the water from our local storm sewers
into the Des Plaines River. The Levee project however includes automated pumping
stations that will pump our stormwater into the river when the backflow valves
close. Only in extreme conditions will the Village need to assist with the
pumping operations in the future. A picture of the frame work and reinforcing
steel for the pump station just south of Seminole Lane is shown below.
 |
 |
 |
|
|
Click on picture for larger image |
|
|
|
July 24, 2009
The installation of the sheet piling continues to move north toward Seminole
(photo below on the left), as the construction of the concrete wall that sits
atop of the sheet piling has moved to near Camp McDonald Road and is progressing
in both directions from there. Pictured below (2nd from the left) is a depiction
of the wall framing and reinforcing bars installation. The tallest part of the
wall above the existing ground level will be just south of Seminole Lane where
the wall will rise approximately 6.5’ above the ground. However from that point
south to the end of the wall near Euclid Avenue the wall will have a much lower
profile. The two photos below on the right show how imposing the wall looks from
the river side (2nd photo from the right) while it looks rather unobtrusive when
viewed from the west side of River Road just north of Camp McDonald Road (photo
on the right).
 |
 |
 |
 |
|
Click on picture for larger image |
|
|
July 10, 2009
The installation of the sheet piling base for the wall is complete from
Milwaukee Avenue to just north of Euclid Avenue, except for a gap between
Seminole Lane and Woodview Drive. The contractor is now installing the sheet
piling near the backflow valves just north of Woodview. Construction of the
Concrete Wall continues south from Milwaukee Avenue along the east side of River
Road. Below are pictures of the curved section at the southeast corner of
Milwaukee Avenue and River Road, a close-up of the finished wall and the wall
under construction.
 |
 |
 |
|
Click on picture for larger image |
|
|
|
July 1, 2009
Except for the flooding event on June 17th, which was successfully handled by
the Village and the Contractor’s large pumps to remove the stormwater out of our
neighborhoods and into the river, the weather has allowed construction to
progress rapidly. The installation of the sheet piling base for the wall is
nearly complete from Milwaukee Avenue to Euclid Avenue. And finally work has
started on the portion of the wall that will be visible. The concrete wall that
will protect our neighborhoods from flooding is rising from the ground and is
impressive. Pouring of the concrete has started at Milwaukee Avenue and is
proceeding south. The wall has an attractive textured finish. Pictures of the
sheet piling and wall construction are shown below.
 |
 |
 |
 |
|
Click on picture for larger image |
|
|
|
June 12, 2009
Construction of Levee 37 continues at a vigorous pace despite the wet weather
we have endured this season. More than 700’ of sheet piling has been installed
along the east side of River Road from Milwaukee Avenue south to near Camp
McDonald Road. If you drive by the site, the sheet piling (pictured below) will
be difficult to see because it is below ground level. Its purpose is to serve as
the base for the concrete levee wall. It is expected that construction of the
concrete wall will start within the next two weeks. The wall will be almost
9,000 long when completed.
In conjunction with the levee construction, the Illinois Department of
Transportation (IDOT) has partnered with the U. S. Army Corps of Engineers and
has agreed to raise the elevation of Milwaukee Avenue west of the Des Plaines
River as part of their Milwaukee Avenue Reconstruction Project. This will serve
as an important component of the levee system. Without raising of the pavement
surface of Milwaukee Avenue, flood waters from the Des Plaines River could run
around the levee wall and still cause flooding into the neighborhoods west of
the river. By raising the roadway, IDOT eliminated the necessity for a gate
structure that would prevent this end around flooding, but also would have
closed Milwaukee Avenue to vehicular traffic during a flooding event. As can be
seen in the picture below, the road raising project is underway. And as the
picture shows, the raising is significant, almost 6.5’ higher than the existing
roadway.
 |
 |
 |
|
Click on picture for larger image |
|
|
|
May 29, 2009
Levee 37 construction is underway. The following work is currently taking
place:
- Excavating for the wall has started south of Milwaukee Avenue and is
proceeding south.
- Sheet piling is being installed at the edge of the river near our outlet
structures just north of Woodview Drive. This will serve as a cofferdam
(temporary levee) around our backflow structures to allow for replacement of
the chambers, which will be built with permanent pumps to drain our storm
sewer system when the river is at higher levels.
- Driving of sheet piling, which will be the base of the concrete levee
wall, will begin also near our outlet structures.
- The first pouring of the concrete levee wall is anticipated on June 1st.
 |
 |
 |
 |
|
Click on picture for larger image |
|
|
|
Groundbreaking Ceremony - March 13, 2009
Groundbreaking ceremonies were held for the long awaited Flood Control
Project called Levee 37 on March 13. This project will provide substantial flood
protection to over 600 residential and business properties located near the Des
Plaines River in Prospect Heights and Mount Prospect and eliminate the recurring
need for sandbagging operations every heavy rain event. The project is a
collaboration between the two municipalities (Mount Prospect and Prospect
Heights), US Army Corps of Engineers, Illinois Department of Transportation,
Illinois Department of Natural Resources, and the Cook County Forest Preserve
District.
The levee will be an 8,500 foot long structure, 500’ of earthen berm and
8,000 of concrete wall. It will be located on the east side of River Road and
Milwaukee Avenue between Euclid Avenue and Palatine Road. The Army Corps has
awarded a contract to Vistas Construction and it is anticipated that the project
will be completed in 2011. The cost of the project is $23 million. Questions
about the project can be directed to Village Engineer Jeff Wulbecker at (847)
870-5640 or
. |
 |
|