The Planning & Zoning Commission review process involves a three-phase
procedure: (1) Staff review of the application and related materials; (2) review
and recommendation by the Village’s Planning & Zoning Commission; and (3) review
and approval by the Village’s Board of Trustees. (Note: There are certain
requests that do not require action by the Board of Trustees). The process
generally can be expected to take from twelve to sixteen (12 – 16) weeks from
the time of initial application through final action by the Village’s Board of
Trustees. The Planning & Zoning Commission review process is outlined below:
|