Storm Sewer Improvements

Print
Press Enter to show all options, press Tab go to next option

Project Information

Important News

 

Dates

 

 

- 6/26/2017 Tentative Construction Start Date

 

 

Documents

 Plans & Specifications
2017 Park Drive Storm Sewer Plans
Park Drive Storm Sewer Project Map

Resident Information Bulletins

 

Contacts

Donna Brown, P.E.

Project Engineer

Mount Prospect Public Works

847.870.5640

publicworksdept@mountprospect.org

 

ALamp Contractors 

Contractor

Overview

On July 23, 2011, the Village endured a record-setting rainfall event that resulted in widespread flooding.  On August 16, 2011, the Village Board commissioned Burns & McDonnell Consulting Engineers to analyze the causes of flooding and present their findings in a comprehensive flood study report.  Burns & McDonnell was also asked to identify cost-effective recommendations to mitigate defined and recurrent flooding problems.

Burns & McDonnell's report was presented to the Village Board at the March 13, 2012, Committee of the Whole meeting.  Its findings and recommendations were subsequently discussed at the April 10, 2012, Committee of the Whole meeting (COW), May 22, 2012, COW meeting, and September 11, 2012, COW meeting.

One of the recommendations from the flood study included storm sewer improvements on Park Drive between Wood Lane and Tano Lane.  The storm sewer improvements include the installation of larger diameter storm sewer main.

Park Drive Storm Sewer Improvements Include

  • Installation of 700 feet of 24inch diameter storm sewer  in the in the street along the east side of Park.
  • Complete resurfacing of Park Drive between Wood Lane and Tano Lane

What Kind of Work Will Be Done

  • Excavating and installing the new storm sewers in the pavement along the east side of Park Drive.
  • Installing manholes, catch basins, and inlets.
  • Regrading and sodding of parkways disturbed during construction.
Schedule
Work along Park Drive is scheduled to begin Monday, June 26.  It is anticipated that the storm sewer portion of the project will be completed by the end of August.  Complete street resurfacing will be completed by the end of October.

 

Will Services To My Home Be Affected

There will be no changes in your regular services such as garbage collection, mail delivery, or emergency services.  Please use caution when driving and walking through the construction zone.

Questions During Construction?
Please visit this project web page for updated information throughout the project.  Should you have additional questions, please contact the Public Works Department at 847/870-5640 or email.